Shell-and-core (stan deweloperski) or turnkey (pod klucz): what you actually get

Published Updated Reviewed 5 min read
Contents
  1. What the law says
  2. What shell-and-core usually includes
  3. What turnkey can mean
  4. Comparing the two options
  5. Costs and time
  6. How the choice affects handover and defects
  7. Which suits you?
  8. Check before you sign
  9. Short answers

Facts being checked

A lawyer or tax adviser is still reviewing this text. Use it to get your bearings, not as legal or tax advice.

Stan deweloperski (shell-and-core, sometimes called "developer standard") means the flat is handed over with walls, floors and installations ready for finishing, but without flooring, a fitted bathroom or kitchen. Pod klucz (turnkey) means it is finished and ready to live in. Neither term is defined by law: what you get is whatever the finishing annex of your developer agreement says, so compare that document, not the sales label.

This article is information, not advice. Prices for fit-out vary widely by city, materials and contractor; get quotes for your own flat.

What the law says

The Developer Act does not define "shell-and-core" or "turnkey". It does require that the developer agreement state the scope and standard of finishing of the flat and the building, and the prospectus must describe the finishing standard too. That description, often an annex with a list of materials, is what the developer is legally bound to deliver.

So when a sales brochure says "high developer standard", ask for the annex. When it says "turnkey", ask what exactly is in the bathroom, the kitchen and the floors, and whether the package is part of the developer agreement or a separate contract.

What shell-and-core usually includes

There is no single standard, and developers differ. The table shows what you will often, but not always, find.

Element Often included Often not included
Walls and ceilings Plastered walls and ceilings Painting, sometimes only primer
Floors Concrete screed Flooring, skirting, tiles
Windows PVC or aluminium windows, sills Blinds, internal sills in some projects
Entrance door Front door with locks Internal doors and frames
Electrics Wiring to points, fuse box, sometimes sockets and switches Light fittings, sometimes sockets
Plumbing Water and drain pipes to points with caps Sanitaryware, taps, shower
Heating Radiators or underfloor heating Thermostats in some projects
Ventilation Ducts and vents Kitchen hood
Balcony Finished floor and railings Lighting, decking

Read the annex line by line: "sockets prepared" is not the same as "sockets fitted", and "radiators" may mean panel radiators of a given type.

What turnkey can mean

"Turnkey" in Poland is used for at least three different arrangements:

  1. A developer finishing package, chosen from a few design schemes, sometimes included in the developer agreement, sometimes signed as a separate contract with the developer or its partner company.
  2. A finishing company recommended by the developer, contracted by you directly.
  3. A flat finished as standard, especially in smaller projects or those built for rental.

Each has different consequences for who is responsible for defects and how you pay.

Watch out: payments under the developer agreement go into the escrow account and are protected by the Developer Act. A finishing package signed as a separate contract may fall outside that protection. Ask the developer to confirm in writing how the package is contracted and paid, and ask a lawyer if it is unclear.

Comparing the two options

Shell-and-core Turnkey
Price at signing Lower Higher (finishing included)
Your control over design Full Limited to the schemes offered
Time to move in Weeks to months after handover Usually soon after handover
Effort You manage contractors or hire a manager Little
Defects in finishing Your contractor's responsibility The developer's or the package provider's, depending on the contract
Financing Fit-out often from your own pocket, unless the bank agrees to include it Can be included in the price you finance
Handover inspection Base finishes only Base finishes plus all finishing work

Costs and time

Market guides in 2026 quote roughly 1,800 to 3,500 zł per m² for finishing a shell-and-core flat to a turnkey standard. That range is wide because a basic finish with standard materials and a premium finish with designer materials are different projects. Treat it as a starting point and get two or three quotes based on your floor plan. You can enter your own per-m² figure in /en/toolbox/buying-costs to see the total cost of buying.

Also budget for:

  • the time between handover and moving in, during which you may pay rent elsewhere;
  • kitchen appliances and furniture, which are not in most turnkey packages;
  • a design project, if you want one;
  • VAT on materials and labour if you buy them yourself.

Ask your bank early whether finishing costs can be included in the mortgage and what documents it would need. Banks handle this differently. Our costs guide lists the other costs of buying.

How the choice affects handover and defects

At handover you check what the developer delivered against the finishing annex. With shell-and-core, focus on flat walls and screeds, correct installation points and windows, because your fitter will build on them. Record defects before any work starts; once tiles or flooring are laid it is hard to prove that the screed was uneven. The handover checklist explains how.

After the transfer, the developer is liable under the Civil Code warranty (rękojmia) for defects in what it delivered. Work done by your own contractor is a separate matter between you and that contractor, so keep their contract, invoices and any guarantee. If your fitter damages something the developer built, expect the developer to point to your contractor rather than accept the claim.

Which suits you?

Shell-and-core tends to suit buyers who:

  • want their own layout of kitchen and bathroom;
  • have time, or someone local to supervise contractors;
  • want to spread spending over time.

Turnkey tends to suit buyers who:

  • live abroad or far from the flat;
  • plan to rent it out soon (see renting out a new-build flat);
  • prefer a single price and a single counterparty.

Whichever you choose, the decisive document is the same: the finishing annex. The step-by-step purchase guide shows where it fits in the process.

Check before you sign

  1. Read the finishing annex and list anything you expected but cannot find.
  2. Check whether materials are named by brand or "or equivalent", and who decides what is equivalent.
  3. For turnkey: confirm whether the package is in the developer agreement and paid into escrow.
  4. Ask for the finishing timetable and what happens if it is late.
  5. Get your own fit-out quotes before you compare prices of shell-and-core and turnkey flats.

Sources

  1. Developer Act (ustawa deweloperska), consolidated text Dz.U. 2026 poz. 880 · accessed
  2. Dz.U. 2025 poz. 1167: Civil Code warranty applies to developers (art. 41a) · accessed
  3. Civil Code, consolidated text Dz.U. 2025 poz. 1071 · accessed

Not advice

This material is for information only and is not legal, tax or financial advice. Confirm the details with a notary, an adviser or your bank before you decide.

Share

Questions

Still wondering? Short answers

Can I change the layout of a shell-and-core flat before handover?

Many developers allow buyer changes (zmiany lokatorskie), such as moving walls or installation points, while the building is under construction, often for a fee and only up to a certain stage. They are not a legal right, so the conditions are whatever the developer offers. Get the agreed changes in writing, with drawings and the price, and check them at handover against those drawings.

Is a turnkey flat a better investment for renting out?

It can shorten the time before the first tenant moves in, which matters if you live abroad or want rental income quickly. But a turnkey package costs more at the start, and the finish may be generic. Compare the package price with local fit-out quotes and with the rent level of similar flats. Tax and lease questions for landlords are covered in our article on renting out a new-build flat.

What does 'or equivalent' mean in a finishing annex?

It lets the developer use a different product of a similar standard if the named one is unavailable. The risk is that 'equivalent' is judged by the developer. Ask for objective criteria, such as the window's heat-transfer coefficient, the door's burglary-resistance class or the tile's grade, so you can compare at handover. If something delivered is clearly below the named product, record it in the handover protocol.

Who is liable if the bathroom leaks after I moved in?

It depends on who did the work. If the bathroom was part of what the developer delivered under the developer agreement, the developer is liable under the Civil Code warranty for defects. If you hired your own contractor, your claim is against that contractor under your contract with them. That is why keeping written contracts and invoices from fit-out contractors matters.

Data

Check it against the data

The same points as in the text, on live prices and registers.

Is your situation different?

Describe it in two sentences. We will say what in this text applies to you and where you need a lawyer.

Describe your situation

We reply in Polish, Ukrainian, Russian and English, usually within one working day.

Elsewhere in the knowledge base

  • Toolbox

    Calculators with stated assumptions: payment, borrowing capacity, buying costs, yield.

  • Playbook

    Procedures from reservation to handover: what to do, in what order, what to check.

  • Questions & answers

    Short answers to what buyers ask most, grouped by topic.

  • Investor notes

    Renting, yield, taxes and risk: looking at a flat as an investment.

Ask a question